|
A Guide to Implementing the Theory of Constraints (TOC) |
|||||
|
P&Q
Answer - Part Four So far we have only had to contend with an internal
constraint – resource B. In the
previous section, part three of the P & Q answer, we had begun to elevate
the constraint by making a small investment, we also had some effective
subordination. We have essentially
reached the stage now where the external market is the constraint. Sure, resource B is essentially fully
utilized, however, it is usually easier to obtain additional capacity than it
is to obtain additional sales. The
question then is – what to do?
Let’s develop the argument further based on the
system as developed to date and using numbers presented by Goldratt for new
market composition and capital investment (1). And although our throughput rate will have
increased slightly ($3.20 for P’s and $2.07 for Q’s) lets use the round
figures from prior to our small change in operating times, therefore;
Like so many small businesses, we find in this case
that capacity doesn’t come in small chunks.
If we are going to elevate resource B and move the constraint into the
market then we must purchase the full equivalent of resource B’s machinery. That is probably OK, but it comes with a
price tag of $100,000. We also need a
second operator for resource B. We are
lucky here because an experienced operator can be had for $400 per week. Our operating expense will have to increase
by this much to accommodate our new outgoing. Being small and prudent, we are not going to rush in
and make this commitment until we are certain that we have a market for the
additional output – and that the additional output is worth our while. However a new market segment has been located. This new market is either geographically or
conceptually isolated from the current market – it is segmented. A point we will return to later. The market is prepared to buy 50 Q’s a week
and in addition up to 100 P’s a week.
Unfortunately due to the nature of the new market segment’s economy
they are willing to pay (after exchange rates) only 80% of the current
rate. Thus these P’s are worth $72
each to us and a Q $80. Previously Q’s were the least desirable of our
products generating $2/min on the scarce resource. Now if we sell additional P’s at $72, less
the material costs of $45 a unit, we will only generate $27. The throughput rate of additional P’s = $27 per 15
minutes or $1.80 per minute. This is less than we currently get from Q’s! In the reductionist/local optima approach selling
below par for additional production would be rejected. However, in the systemic/global optimum
approach we can understand that so long as the market is the constraint, any
additional sales that exceed raw material costs will make a positive
contribution to the bottom line. After
all we have already “covered” our operating expenses with our previous
sales. Whether the contribution is
sufficient in this case to justify the additional investment needs to be
determined. Let’s do that. We have tabulated all the new data and increased
operating expenses to cover the additional worker. We have twice as much time available on B
as we did before.
We set out initially to capture more of the market
for P because we knew that they generate 50% more throughput than Q
does. However, in the process of
elevating resource B we broke a constraint, and now we must locate the new
constraint before any meaningful analysis can be made. In this system where the likely candidates
– resource C & A both have the same total capacity we can make a
reasonable guess that resource A with 15 + 10 = 25 minutes will be more
likely to be constrained than resource C with 17 + 7 = 24 minutes. Therefore let’s evaluate resource A as the
constraint. To do that we need to establish the new throughput
rates. For example P would be 45/15 =
$3minute – just as before. Q would be
60/10 = $6 minute. Oops. Is that
correct? The order seems to have been
changed around. Q’s are now twice as
profitable as P’s! Let’s tabulate this
for both old P & Q’s and additional P & Q’s.
It seems surprising at first, Goldratt explains it
thus; “… in the ‘cost world’ almost everything is important, thus changing
one or two things doesn’t change the total picture much. But this is not the case in the ‘throughput
world.’ Here, very few things are
really important. Change one important
thing and you must re-evaluate the entire situation.” We change one important thing here – the
location of the constraint, and therefore we must re-evaluate the entire
situation. In real life the number of options the constraint
can move to are limited, and often well within control. They in fact become strategic decisions
based upon where it is most desirable to have the constraint. Let’s work through the calculations step by
step. Let’s sell as much as possible
of the best performer using resource A and then move on to the next. We can sell 50 *10 = 500 minutes of Q which leaves
us with 2400 – 500 = 1900 minutes We can sell 50 *10 = 500 minutes of Q’ which leaves
us with 1900 – 500 = 1400 minutes We can sell 100 * 15 = 1500 minute of P. We don’t have that much. Let’s try the other way around. 1400/15 = 93 Ps. Let’s plug this into the table and see what we have.
Ah ha! If we
make a commitment to this market, and we break our current constraint as
intended by purchasing another resource B and a machine, then we will make
$2785 per week – up from $540 per week at present. So we don’t even double sales (we can’t supply the
demand at all for additional P’s) and yet our profit increases (2785-540)/540
= 400%. Should we do it? Look at it another way, payback on the capital will
be 100,000/(2785-540) = 45 weeks. Less
than a year. I’ll let you make your
own decision. Let’s go over what we have discovered in these 4
sections. Firstly we learnt the
identity of the constraint or scarce resource when we couldn’t meet our
aspirations to sell all the market demand.
Such accidental acquaintance with a constraint isn’t so unusual
either. Then we learnt how to best
exploit the current situation by ensuring that we produced the maximum
throughput per unit time on our scarce resource. Next we elevated the scarce resource a
little by some incremental capital investment and our profit rose
substantially. We also had to
subordinate one of the non-constraint resources at the same time in order to
do this. Finally we set out in search
of additional market and additional capacity.
We found that breaking a previous constraint can have important
ramifications on our future decisions.
However once we aligned those decisions with our experience in
maximizing throughput we once again surprised ourselves with the increase in
output that could be achieved. The objective is to turn that knowledge into
effective implementation in real life.
The process is the same and the results just as effective as we shall
see. Let’s return to the measurements page. To return to the previous page press Alt key + left arrow. (1)
Goldratt, E. M. (1990) The haystack syndrome: sifting
information out of the data ocean.
North River Press, pp 93-99. This Webpage Copyright © 2003-2009
by Dr K. J. Youngman |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||